Planes of official delegations stir the reconstruction of Terminal "B" at the international airport "Borispol". Airport Boryspil transfer Kiev taxi agency have informed about this in the press-service of the Ministry of transport and communication of Ukraine.
«Backlog from the schedule speaks breaks in work connected with service of planes with official delegations as the building site is in immediate proximity to a hall, serving officials».
According to department «for today terminal reconstruction is executed on 67 %».
«At the given stage works on a starting complex 1, 2 and 3 are finished. The starting complex 4 is completed on 50 %, a complex 5 – on 10 %. Works on arrangement of entrance group, passenger gallery and on building of a luggage space of a starting complex 4» are spent.
In the Ministry also have noticed that «working out and the coordination of the design documentation on terminal" D "building proceeds. On terminal" F "commissioning term for August-September, 2010 is transferred. Works on internal arrangement of air terminal, installation of technical networks» here proceed.


Humidity: 88%